Page 11 - Energize June 2021
P. 11

NEWS



        in the supply chain, and how these
        livelihoods could be affected by standards   Unique projects call for unique solutions
        imposed by Europe.
           “The intent of this initiative is to   B Switchgear Solutions was recently awarded a contract to design, manufacture,
        optimise positive impacts generated      and supply four containerised substations for the Gbeni site of Sierra Rutile’s
        by the way that minerals are sourced,”   Jmining operations.
        said Lisl Pullinger, principal consultant -   This was a unique project since the containers each had to house a MV/LV dry type
        ESG at SRK Consulting. “How we define   transformer and electrical switchgear. This containerised equipment had been put onto a
        responsible sourcing forces us to ask the   skid and these skids were built to be movable around the mining site.
        difficult questions about how sourcing   The substations/skids were broken up into four: Two booster skids/substations, one
        standards could have unintended effects   mining in-pit skid/substation and a scrubber skid/substation.
        on livelihoods in Africa. If livelihoods   The containers for the booster skid and mining in-pit were made into 7 m lengths
        are undermined, for instance, are those   and were split at the mid-point by a partition wall, so that one side housed the dry-type
        standards really responsible?”        transformer, and the other side housed the LV panels.
           Pullinger highlighted that the process   The booster substations were also 7 m long, and each housed an 800 kVA dry type
        is even more relevant in the context of   transformer on the one side of the container and the LV panels on the other side.
        economic disruption due to the Covid-19   The LV section housed the MCC, which consisted of an incomer rated at 1250 A, which fed
        pandemic, where the inequalities      two 260 kW free standing variable speed drives (VSDs) in the container. These VSDs were used
        between regions have been brought into   for the slurry pumps on the skid. The LV section of the container housed a 250 A PFC panel as
        stark contrast.
                                              well, which was fed from the MCC.
        Engagement vital                         The mobile mining unit/mining in-pit substation was also 7 m long and housed a 1600
        One of SRK Consulting’s functions will   kVA dry type transformer on the one side of the container. The LV section housed the MCC,
                                              which consisted of an incomer rated at 2000 A, which fed two 160 kW soft starters, as well as
        be to facilitate the input of a forum of   a 355 kW free standing VSD, which is used for the gravel pump. The LV section of the container
        stakeholders from around sub-Saharan   housed a 400A PFC panel, also fed from the MCC.
        Africa next year, said Van Zyl.          The scrubber substation was initially a 12 m container, but due to skid restraints, was
           “This process should have wide     cut into half, thus becoming two containers, with one feeding the MCC panels in the other
        interest and engagement, allowing     container via an encapsulated busbar system.
        organisations to flag possible unintended   The set up was the same as the previous containers. One of the 6 m containers was
        consequences of future European       divided to accommodate the 2000 kVA dry type transformer which fed the LV panel with an
        directives aimed at responsible sourcing   encapsulated bus-bar system. The LV section housed the MCC which featured a 2500A incomer.
        – before those directives are applied,”   The panel consisted of 15 DOL starters, plus a few feeders.
        he said. “This recognises that there are   The second incomer had a second incomer rated at 2500A as well, which was fed from the
        many national standards to which mines   first container. This container housed a 200 kW wall mounted VSD for the water booster pump,
        already comply, which do not need to be   two 260 kW VSDs for the trommel underflow pump, and two 330 kW VSDs for the scrubber
        reinvented. These standards have been   trommel. The LV section of the container housed a 400A PFC panel, also fed from the MCC.
        developed following ongoing, pro-active
        engagement between stakeholders.”     Contact JB Switchgear, Tel 011 027-5804, info@jbswitchgear.co.za
           He highlighted that there was potential
        for significant disruption to supply chains
        originating in Africa, if any directive
        happened to include well-intentioned
        requirements that were difficult or
        impossible to comply with.
           “We expect the mining sector to be
        enthusiastic about participating in these
        consultations, as it is both a good risk
        management strategy and an effective
        way of providing price support for acting
        responsibly,” he said. “Those responsible
        miners – who have chosen to embrace
        both the opportunities and challenges of
        responsible mining – can only gain from
        well-considered responsible sourcing
        standards being applied to every player in
        the sector.”

        Contact SRK, Tel 011 441-1111,
        johannesburg@srk.co.za,
        www.srk.co.za



                                                    energize | June 2021 | 9
   6   7   8   9   10   11   12   13   14   15   16