Page 24 - Waterfall City Special Edition 2022
P. 24

With the first of three facilities of its Waterfall City campus   phase of construction, and we thank our teams for their
                       now operational,  Vantage Data Centers is poised for   dedication and determination to deliver such a high-quality
                       expansion into Africa. After breaking ground in 2021,   product for our customers.”
                       the project was delivered 10 days ahead of schedule, in a   The campus has been designed to meet Vantage’s strict
                       mere 10 months. The two-storey facility offers 16MW of IT   standards for sustainability, security and dependability
                       capacity across 12 000m².                      that customers have grown to expect and rely on. As part
                         From cloud solutions to mobile applications and the   of  Waterfall City, the campus complements the area’s
                       advanced Artificial Intelligence (AI) capabilities that are   thriving smart city ecosystem and leverages its fibre
                       likely to disrupt and redefine how we live, work and play,   connectivity to the rest of Africa. In addition, the campus
                       the technologies of tomorrow are all dependent on one   aligns  with the company’s  commitment to  sustainability,
                       thing – a data centre, a dedicated facility for servers and IT   the use of renewable energy, limiting carbon emissions,
                       equipment. Scaling this up, a hyperscale (wholesale) data   and maintaining energy efficient operations with an
                       centre comprises hundreds of thousands of servers.  industry-leading power usage effectiveness (PUE). In June
                         Situated  on  30  acres  (12ha),  Vantage’s  carrier‐neutral   2022, Vantage announced it had entered a 20-year power
                       Waterfall City campus will include 60 000m² of data space   purchase agreement (PPA) with SolarAfrica to support the
                       across three facilities, once completed, making it one of   production of 87MWp of renewable energy to supplement
                       the largest on the continent. Comprising 80MW of critical   the local grid that powers the campus.
                       IT load, the campus will help foster economic growth,   The design of the campus follows Vantage’s standardised
                       stimulate job creation and lead the way in energy-efficient   blueprint, which specifies natural site drainage, water-
                       design.                                        wise and drought-resistant landscaping, motion-sensor
                         “Our  rapid  turnaround  on  the  construction  of  our  first   LED lighting, electric vehicle charging stations and on-site
                       Johannesburg facility has allowed us to more quickly   recycling.
                       meet demand for hyperscale data centres in the area,” says   Attacq CEO, Jackie van Niekerk, says, “With a scalable,
                       Justin Jenkins, Chief Operating Officer, EMEA at  Vantage   fit‐for‐future logistics hub and a world‐class corporate
                       Data Centers. “At Vantage, we pride ourselves on not only   campus, Waterfall City has an established track record of
                       our speed to market, but also our commitment to become   attracting leading international businesses, like Cisco, BMW,
                       part of the local community and cement our reputation   PwC, Massbuild, Cotton On and Cummins, to the precinct.
                       as a reliable data centre partner in the region. This project   As the developers of Waterfall City, Attacq is working with
                       created hundreds of jobs that will continue into the next   Vantage to complete a campus that is tailored to meet the



          22   |   WATERFALL CITY SPECIAL EDITION