NEWS


                 A civil engineering project well worth its ‘salt’





              rinaker-LTA’s role in the                                           The firm’s civil engineering division’s
              Redstone Concentrated Solar                                         scope of work in the thermal power
       GThermal (CSP) power plant                                                 plant consists of:
        project in the Northern Cape, which is                                    •  Steam generation structure
        the largest investment made to date                                       •  Molten salt pump structure
        in terms of South Africa’s Renewable                                      •  Hot salt storage tank
        Energy Independent Power Producer                                         •  Cold salt storage tank
        Procurement Programme (REIPPPP),     project-financed CSP with molten salt   •  Water treatment plant civils
        consists of the construction of various   central receiver in the world, and also   •  Fire protection water pump house
        permanent civils work. Abdool Shaikh,   one of the largest investments in South   civils
        Managing Executive of Grinaker-LTA’s   Africa under the Programme. Following   •  Demineralised water storage tank
        Civil Engineering division, said that   commissioning, commercial operation   •  Effluent collection area
        President Ramaphosa, together with   is scheduled to commence towards the   •  Retaining wall
        the client and an entourage comprising   end of 2023. With 12 hours of full-load
        various government members and local   energy storage, Redstone will be able to   The company’s section of the
        dignitaries, took part in a site visit to   reliably deliver a stable electricity supply   project was due for completion in
        Redstone CSP power plant in October.   to more than 200 000 South African   December 2022 – with the overall
        The 100 MW Redstone CSP plant, which   homes during peak demand periods,   project scheduled for completion
        forms part of the REIPPPP, is the first   even well after the sun has set.  in 2024.


         Contract to supply a massive battery system in the UK





              he technology group Wärtsilä has signed a contract with   and GEMS Digital Energy Platform, in addition to the power
              EDF Renewables UK and Ireland to deliver a new grid-scale   conversion system and commissioning for the project. GEMS
         Tenergy storage facility in Sundon, Bedfordshire, UK. The   provides the data and insights to instruct trading parties and
         50 MW / 100 MWh project, which will form part of a new Energy   performance for comprehensive asset management. The energy
         Superhub in the region, will help to support the transition to a   storage technology will enable balancing services for the UK grid,
         decarbonised electricity system and accelerate the UK’s net zero   including electricity market trading and frequency response, with
         future.                                              the capability to support local consumers such as EV charging
            The new Li-ion storage facility, which can store enough   stations during grid outages.
         electricity to power 100 000 homes for two hours, will support
         electric vehicle charging and the electrification of public transport.   Contact Mirja-Maija Santala, Wärtsilä Energy,
         The project will enable increased renewable energy integration   mirja-maija.santala@wartsila.com
         and intermittency management, in addition to strengthening the
         resiliency of the electricity system, automatically charging and
         discharging to balance supply and demand.
            Matthew Boulton, a director at EDF Renewables, says there
         is no renewable future without a smart, flexible energy grid.
         “That is why we are working with local councils to accelerate the
         rollout of Energy Superhubs, helping to unleash the potential of
         renewable energy and enable local people to reap the benefits of
         net zero through better access to low-carbon transport. We know
         the challenge ahead of us – we need more renewable energy and
         energy storage to back it up. Our storage facility in Sundon marks
         a key milestone for the UK as we lay the foundation for net zero.”  Wärtsilä’s innovative 50 MW / 100 MWh energy storage solution to
                                                              Sundon, UK supporting the UK’s transition to a decarbonised electricity
            Wärtsilä has provided its propriety GridSolv Quantum system   system © Wärtsilä Corporation