POWERING DATA CENTRES


              Eaton installs its largest African


             modular power system at Africa



                     Data Centres’ Midrand site








            aton announces the successful installation of a
            modular power system earlier this year at Africa Data
       ECentres’ 10 MW facility - its largest installation on the
        continent to date.
           When the largest pan-African network of interconnected
        data centre facilities, Africa Data Centres, grew its business to
        include data storage solutions, it required significant upgrades
        and improvements to expand the capacity of its legacy building
        in Johannesburg. The enhanced facilities had to meet data
        centre site requirements with supporting power solutions – all
        of which had to be configured to fit into a very limited space
        and accommodate a restricted on-site installation time.
           Despite time and space constraints, and difficult operating
        conditions, Eaton delivered a configurable xModular power
        system that extended the electrical infrastructure of the facility
        without interfering with day-to-day operations, providing an   it is a self-contained system with a patented design, which allows for
        innovative ‘plug and play’ solution that is scalable for easy   different types of scalabilities and better redundancy that may not
        upgrade in the future.                               be provided by a more conventional UPS,” says Armand van Niekerk,
           According to Tesh Durvasula, CEO of Africa Data Centres,   Data Centres Segment Lead for Africa at Eaton. “It is easy to install,
        “Due to the nature of our business, on-site installation time   upgrade and reconfigure, saving considerable time and costs for
        had to be restricted and limited to final assembly and cable   businesses.”
        connections only.”                                      “The air-insulated Power Xpert UX IEC withdrawable medium
           To address these prerequisites, Eaton built the modular   voltage switchgear offers world-leading vacuum technology in a
        units off-site at its manufacturing plant in Germiston, and   compact footprint and arc flash classification, making it a safe,
        planned and managed the process of delivering the weighty   reliable, efficient choice as part of this solution. Additionally, the
        units by road, using specialised trucks and air-suspension   Eaton Power Xpert 9395P UPS offers complete isolation of output
        loading trailers, and then lifting them into place using specially   power from all input power anomalies to deliver 100% conditioned,
        hired 700 T cranes.                                  perfect sine-wave output, even during severe power disturbances,”
           “Apart from physical requirements, we expected    says van Niekerk.
        the solution to offer stability and reliability under all   He adds that the Energy Saver System built into the installation
        environmental and power supply conditions, in a robust   improves efficiency levels by 99% by placing power modules on
        prefabricated structure. Adequate load handling capabilities   standby when double conversion is not required. The system
        were essential, as well as ease of operation and maintenance,”   can however switch to double conversion mode in a matter of
        Durvasula said.                                      milliseconds if required.
           The solution was expected to offer a total integration of   Other benefits of the tailored modular system include continuous
        Eaton products into one system with an approach intended to   function by the energy saver system at ambient temperatures of up
        protect the data centre from the repercussions of inconsistent   to 40 degrees Celsius without de-rating. In addition, the UPS is easily
        power supply and the ongoing ‘load shedding’, or power   scalable, the number of power modules can be specified, and the
        blackouts, that South Africa has become accustomed to.  layout can be chosen to suit the installation. With more than 90%
           Eaton’s fully integrated turnkey solution included the   of materials used in its manufacture able to be recycled, this will
        Power Xpert UX IEC withdrawable medium voltage switchgear,   significantly reduce their lifetime carbon impact.
        the Eaton Power Xpert 9395P UPS, and Eaton’s lithium-ion   “This is an easily adaptable design that can be duplicated and
        battery combinations.                                rolled out as a turnkey solution for other partners in the future,”
           “As part of the design we installed Eaton’s modular UPS as   concludes van Niekerk.                  n


                                                 EngineerIT | December 2022 | 21