Page 36 - Energize March 2021
P. 36

TECHNICAL

        Design modifications at Medupi and



        Kusile: progress and problems





        by Chris Yelland, EE Business Intelligence



        Much has been written about the cost and time overruns at Eskom’s flagship new-build mega-projects
        – the Medupi and Kusile coal-fired power stations in South Africa. This article focuses on the boiler plant
        design defects and the status of rectification work currently in progress.








            he Medupi and Kusile projects    The planned modifications required on each of the twelve units at Medupi and Kusile include:
            involve the construction of two   -   Mills: Eleven modifications were agreed to be implemented – initially in a matrix across
        T4800 MW, coal-fired, direct dry-      the five mills of Medupi Unit 3 to determine the performance of the modifications and
        cooled power stations. The Medupi      their interdependencies.
        site is close to Eskom’s Matimba     -   Pulse jet fabric filter (PJFF) plant: The modifications include redirecting the flue gas inlet
        power station in the Lephalale district   to the bag filter and equipment changes to the pulsing systems used for cleaning the
        of Limpopo Province. The Kusile site   fabric filter bags during operation. A new set of fabric filter bags are also to be installed
        is close to Eskom’s existing Kendal    after the modification.
        power station in the Nkangala District of   -   Gas air heater (GAH): Modifications to the gas air heaters include internal erosion
        Mpumalanga Province.                   protection and modifications to the pin rack driving the rotation of the gas air heaters.
           An article in Engineering News on   -   Hot air duct erosion: Solutions for erosion protection in the various hot air ducts include
        1 February 2019 summarised a number    fitting of ceramic tiles and combinations of ceramic tiles and wear resistant metal plates in
        of technical defects identified by Eskom   the hot air ducts.
        at Medupi and Kusile that were causing
        serious underperformance at the power   The first unit of the six units at Medupi to be reworked was Unit 3 during a 10-week shut down
        stations. The generation units handed   from the last week in January 2020 to the first week in April 2020. Although Unit 3 at Medupi
        over for commercial service were     was intended as a “proof of concept”, work on the design modifications of further units at
        unable to operate at full load and were   Medupi commenced even before performance testing of the modifications on Unit 3 was
        experiencing frequent planned and    completed, as shown in Figure 1.
        unplanned outages.                     One of the five mills on Medupi Unit 3 was used as the reference mill without any
           Thereafter, an open letter written   modifications, and one mill as the reference mill for all the modifications. Modifications on the
        by Mr Alex Ham, a former Eskom Chief
        Engineer: Power Station Design, and later,
        Director of Technology, who had worked
        for the utility for 30 years, was published
        by EE Publishers on 12 May 2019. The
        letter spelled out the background to the
        boiler and mill problems at Medupi and
        Kusile in further detail.
           In order to rectify these defects,
        Eskom and the boiler works contractor,
        Mitsubishi Hitachi Power Systems Africa
        (MHPSA) are now undertaking significant
        rework of all twelve units at Medupi
        and Kusile. This requires that each unit
        be shut down for about 75 days, in
        sequence, to conduct the necessary
        rework, with the associated costs shared
        50/50 between Eskom and MHPSA,
        pending resolution of the contractual
        matters between them.                Figure 1: Timelines for rollout of contractor boiler plant technical solutions. (Source: Eskom)



                                                    energize | March 2021 | 34
   31   32   33   34   35   36   37   38   39   40   41