Page 37 - Energize March 2021
P. 37

TECHNICAL



        other mills included combinations of items that could be manufactured quickly in combination   systems for which the design modifications
        with off-the-shelf equipment, and long manufacturing lead-time items that needed to be cast.   were done, or due to other plant systems
           Tests on Medupi Unit 3 indicated positive results for all mill modifications, and the   – of which there are many – on which no
        implementation of the items with short manufacturing and procurement lead-times were   modifications were done. Eskom says that
        rolled out. Manufacturing of the mill items with long manufacturing lead-times were   although the availability of the systems on
        started immediately after the rollout decision and will be rolled out during upcoming unit   which design modifications were done did
        and mill outages.                                                         improve, this improvement was negated
           A year after the project started, there is still a significant amount of modification work to   by unforeseen once-off events in other
        be done on all the remaining five units at Medupi. These include the manufacturing of long   unrelated sub-systems.
        lead-time items on the mills, the gas air heater operational modifications, and the boiler low   Furthermore, Eskom explains that
        load modifications. No work has yet commenced on the design modifications of the six units   the EAF of Unit 3 was pushed down by
        at Kusile.                                                                increased planned outages after the
           Considering the Medupi Unit 3 performance figures shown in Figure 2, there does not   shutdown due to extra-ordinary planned
        appear to be that much difference in energy availability factor (EAF) before and after the   maintenance in preparation for performance
        design modifications. However, a careful analysis of the EAF for the past 50 weeks since the   verification tests of the modifications done.
        10-week shutdown in early 2020 indicates an average EAF of 75%, which is an improvement   “Typically, you would need a longer period
        of the EAF of below 70% before the modifications.                         to evaluate performance, in order to even
           However, the week-on-week EAF for Medupi Unit 3 is still erratic, with ongoing high   out the impact of such unforeseen events”,
        levels of planned (PCLF) and unplanned (UCLF) outages, and certainly not what one would   says Eskom.
        expect from a properly functioning, relatively new, base-supply unit that underwent a major   However, Eskom has acknowledged
        10-week rework outage a year earlier. One may expect the average EAF in such a case to   that performance of the pulse jet fabric
        be more like 85% to 90%, which is still below the 92% “use requirement specification”   filter plant after the rework has been
        target set for the units.                                                 disappointing. The lifetime of the fabric
           Eskom indicates that this continuing sub-par performance can either be due to sub-  filter bags before replacement has only
                                                                                  increased from nine months to thirteen
                                                                                  months, instead of the 36 months expected
                                                                                  in the “use requirement specification”.
                                                                                    What has become clear, though, is
                                                                                  that there is still a long way to go before
                                                                                  the Medupi and Kusile coal-fired power
                                                                                  stations will operate at the level of
                                                                                  performance originally intended. Indeed, it
                                                                                  is becoming apparent that this performance
                                                                                  will likely never be achieved.
                                                                                    The direct costs of the efforts to
                                                                                  improve the performance of Medupi and
                                                                                  Kusile, the indirect costs of their poor
                                                                                  performance on lost production and lost
                                                                                  sales, and the cost to the economy due to
                                                                                  load shedding, is truly enormous and still to
                                                                                  be calculated.                n

                                                                                  Send your comments to
        Figure 2: Medupi Unit 3 performance before and after the design modifications. (Source: Eskom)  rogerl@nowmedia.co.za



























                                                    energize | March 2021 | 35
   32   33   34   35   36   37   38   39   40   41   42