Page 27 - Energize April 2021
P. 27

VIEWS AND OPINION


       Understanding decisions behind SA’s


       “emergency” power programme



        by Chris Yelland, managing director, EE Business Intelligence



        This is a summary of three interviews which explore the rationale, outcomes, and some of the details of the
        recently announced Risk Mitigation Independent Power Producer Procurement (RMIPPP) programme.







        Here, Chris Yelland seeks to clarify some of the contractual   Furthermore, there are entities who did not bid because they felt they
        arrangements applicable to all the RMIPPP projects, with   would not be able to meet the tight timelines.
        Department of Mineral Resources and Energy Deputy Director   So, the justifiable interests of South Africa, the procurer, off-
        General, Mr Jacob Mbele, and IPP Office Acting Chief Operating   taker, customers, and end-users must be balanced with those of
        Officer, Mr Maduna Ngobeni.                            the preferred bidders, and one cannot simply give unwarranted
                                                               additional time to reach financial closure or commercial operation.
        Chris Yelland:                                         These things get considered looking at the project but most of the
        Minister Mantashe stated that preferred bidders are required to reach   risk lies with the bidder.
        financial close by no later than the end of July 2021, that this date is
        non-negotiable, and it is for the preferred bidder to manage all the   Chris Yelland:
        risks to reach financial close. He further indicated that the projects   Before reaching financial closure, what other hurdles are required
        are expected to be connected to the grid from August 2022. What   to be crossed by preferred bidders? For example, do the preferred
        will be the consequences to preferred bidders, electricity customers   bidders have exemption by the DTIC from the local content
        and the public if the preferred bidders fail to achieve financial closure   requirements of the RMIPPP procurement process yet? Do they
        by 31 July 2021, and power to the grid by August 2022? Are there   have final environmental impact assessments and climate change
        any penalties applicable?                              studies that are not subject to appeal? Do the powership projects
                                                               have all the required permissions from the Port Authorities to moor
        Yes, there are consequences for a preferred bidder failing to achieve   the powerships and associated fuel storage and re-gasification
        financial closure and commercial operation by the target dates. If the   plants for 20 years?
        dates for financial closure or commercial operation are not met, the
        bid bond can be pulled, or the power purchase agreement (PPA) can   Yes, there are certainly several things that need to be attended to.
        be terminated.                                         But obviously, for most of these, it is the preferred bidders’ risk and
           Obviously, one must always look at the reasons for not meeting   responsibility. We know of and are involved in a few issues. But there
        the contractually required dates. For example, is it a force majeure   is a whole lot more that the bidders need to do, in which we do not
        situation or not? Did the Covid-19 pandemic delay things? Was   get involved. The preferred bidders should manage these to make
        everything ready on our side? Was Eskom ready with the grid   sure they bring their projects to fruition.
        infrastructure and lines to evacuate the power?           You mentioned environmental authorisations and climate change
           Depending on the reasons for delays, the contractual timelines   impact studies, and whether there may be any appeals in respect of
        may need to be adjusted. The preferred bidder must meet the   these. What we required from a bidding point of view was a scoping
        contractual timelines, and if not met, there are consequences. There   report, and that is what we received. Regarding applications for
        are many provisions in the contract to remediate a breach situation   actual environmental authorisation, I would assume that the preferred
        before it leads to termination. However, at the end of the day, the   bidders have already started and are busy with these things,
        bottom line is that the PPA may be terminated.         because it is their responsibility to make sure these are sorted out.
           There are financial penalties in the sense that if the preferred   Other requirements include authorisation from the Port
        bidder cannot achieve financial closure or commercial operation,   Authorities, as you mention, as well as generation licences from
        and the PPA is either not signed or is terminated, the bidder would   Nersa. It is the responsibility of the preferred bidders to sort out
        already have lost a lot of money. In addition, we do hold guaranteed   these things. There are risks, and the preferred bidders need to
        bid bonds from the preferred bidders amounting to some R200   manage them. We told them what is needed for them to be eligible
        000 per MW of capacity bid. If a preferred bidder does not meet its   for the licensing of their works for the duration of the PPA. They
        obligations for financial closure or commercial operation, we would   know this, and I presume they are working on it.
        pull the bid bond.                                        We don’t necessarily really get involved in worrying about
           Of course, the economy and electricity customers will suffer if   appeals and things that are the responsibility and within the control
        the power is not delivered on time, and this needs to be appreciated.   of the preferred bidders at this point.



                                                    energize | April 2021 | 25
   22   23   24   25   26   27   28   29   30   31   32