Page 19 - Issue 3 2023
P. 19

TECHNICAL



           would have resulted in a TC factor
           close to unity for all three bushings –
           valid for bushings H1 and H2 but not
           for H3.
        •  Bushing H3 would have been
           removed in this scenario due to a   Table 3: Pre-installation C1 test results for new H3 replacement bushing, 10 kV LF PF and 250 V NB DFR
           >1% PF value. However, had the
           bushing been tested at 10°C instead
           of at about 30°C, its measured and
           temperature-corrected PF test results
           by look-up tables may have been low
           enough to pass acceptance criteria as
           a normal, service-aged unit.


        Given the LF PF test results, the utility
        performed NB DFR tests on the high-side
        bushings. 1 Hz and 505 Hz measurements   Table 4: 10 kV overall transformer LF PF test results after H3 bushing replacement
        from this testing are provided in Table
        2. These tabular results affirm the good   With the problem corrected in the overall winding insulation test results, the utility
        condition and rating of bushings H1 and   staff then complemented their now-routine procedure with a 10 kV LF PF test on the
        H2 but escalate the assessment of the H3   installed H3 replacement bushing (Table 5).
        bushing to an investigate rating.      The 10 kV measured LF PF test result for the H3 replacement bushing was acceptable.
                                             However, the ITC temperature-corrected LF PF result is about 1,5 times the measured
        NB DFR test results for bushing H3   value, while the 1 Hz measured, and ITC temperature-corrected results are nearly the
        (the blue trace in Figure 1) revealed
        the following two worrisome electrical
        characteristics and the utility replaced
        the bushing.
        •  A bushing in good condition will have
           an ITC temperature-corrected PF value
           ≤1% at 1 Hz. The ITC temperature-
           corrected 1 Hz PF test result of
           bushing H3 was 7,92 % (Table 2).
        •  The 10 kV LF PF test result, 1,1 %
           (Table 2), and the LF PF test result
           at 250 V, a typical NB DFR test
           voltage, taken from Figure 1, 0,8 %,
           are different. This implies a voltage
           dependence of the LF PF test results.
                                             Figure 1: NB DFR measured test results for the high-side 69 kV bushings
        Before installing in the transformer, LF
        PF and NB DFR testing was performed on
        the H3 replacement bushing to confirm
        its integrity. LF PF and NB DFR test
        results indicated the bushing’s good (G)
        condition (Table 3) (Figure 2).
           After replacing the H3 bushing, the
        utility repeated the overall LF PF tests
        on the transformer to observe what
        effect the H3 bushing replacement had
        on the overall HV winding insulation test
        characteristics (Table 4). There was a
        notable improvement.                 Figure 2: Pre-installation NB DFR test results for H3 replacement bushing


        SUBSCRIBE FREE                                                                         energize Issue 3 | 2023 | 19
   14   15   16   17   18   19   20   21   22   23   24