Page 55 - Energize August 2021
P. 55

TECHNICAL



        up to have enough capacity to serve the
        load. The case presented above considers
        a significant amount of solar penetration.
           In order to make the system more
        resilient and stable to the intermittent nature
        of solar fluctuations, a battery storage
        system is added to the system. There are
        various roles a battery storage system
        can play, including PV output smoothing,
        frequency control and load shifting.
        Further, the battery storage system serves
        as a spinning reserve replacement when
        switching off engines is required, to cover
        unforeseen events or to provide sufficient
        time to start gensets. Consequently, its
        capacity would need to be added to the
        blue dotted line shown in Figure 2.
                                             Figure 3: Some of the results from the case study with solar capacity of (a) 10 MW; (b) 20 MW; (c) 30 MW; (d) 50 MW
           The battery’s main function is to
        smooth the solar output and keep
        engine operation and ramping within   Case study analysis
        operational requirements. The steep spikes   A case study was carried out on the above-mentioned off-grid hybrid system to assess the
        (represented in light yellow) show an   electricity cost reduction potential when hybridising existing HFO genset based power. The
        exemplary fluctuation of solar power due   study was conducted for a fictious mining site in Burkina Faso with a total load demand of 30
        to a small cloud cover, which is absolved   MW. This load demand was originally served by seven HFO gensets of 5 MW each.
        by discharging the battery. The genset   The sizes of the solar and battery systems were varied and the renewable energy (RE-
        operation therefore only sees the smoothed   share) penetration and levelised cost of electricity (LCOE) produced by the overall system
        output of the hybrid system represented by   including HFO cost of electricity, were accessed as the key performance indicators. It was
        the red line.                        assumed that any realistic size of solar and the battery systems could be integrated with the
           From Figure 1 it can be seen that the   existing gensets and all technical requirements and possible constraints can be managed.
        battery and the solar plant are a combined   Figure 3 shows some of the example cases which were considered during the case study.
        system and any power produced from the   The size of the solar system is increased as the percentage of load, from 30% to over 150%
        solar plant is smoothed through the battery   in these cases. At higher solar penetrations, the remaining HFO gensets are not sufficient to
        storage system by a hybrid controller. This   stabilise the grid, as too many gensets are switched off. Hence batteries must act as a grid-
        hybrid controller decides if the battery   forming component to the system with sufficient power and capacity to ensure reliable and
        shall be charged or discharged or if and   stable operation.
        when genset capacity needs to be added   Further, the HFO fuel system needs to be kept in hot conditions for genset operation.
        or switched off. Another key element of a   The required heat is usually provided through gensets under operation. In scenarios where all
        hybrid system is solar power forecasting.  gensets are switched off, an electrical heater system is powered by the solar-battery hybrid
           The above-mentioned hybrid controller   plant. At very high solar penetration and thus RE-share as seen in Figure 3(d), the battery
        requires a forecasted solar power to   also provides load shifting services in addition to the smoothing and grid stability. Excess
        efficiently determine a suitable generator   solar energy is used to charge the battery which can be discharged during the evening hours.
        dispatch schedule and identify any loss   While assessing the economics of the system, various assumptions must be made. Table 1
        of solar power production sufficiently in   summarises the technical and financial assumptions which were considered during this study.
        advance to switch on gensets. In the case
        of HFO based gensets, this is vital since
        it can take 10 to 30 minutes to start an   Parameter                       Value         Units
        engine. Without solar power forecasting,   Total load demand               30            MW
        the decision whether a genset can be
                                              Number of HFO gensets                7             –
        switched off or would need to be online
                                              Derated capacity of each genset      5             MW
        in 15 minutes cannot be made. The
                                              Lifetime of the mine                 10            Years
        forecasting enables this decision and helps
        to maximise fuel saving through efficient   Mine availability              93            %
        genset operation.                     HFO fuel price                       0,64          US$/litre
           There are different types of forecasts   OPEX cost escalation           2,5           %
        available depending on the required
                                              Annual solar irradiation             2155          kWh/m2
        forecast duration. For up to 30 minutes, a
                                              Specific yield for single axis tracker system   2095   kWh/kWp/year
        sky imager is required, whereas satellite-
                                              Solar system CAPEX                   720           US$/kWp
        based forecasting combined with digital
        weather prediction can efficiently forecast   Battery CAPEX (1C rated)     440           US$/kWh
        from 30 minutes to several days ahead.  Table 1: Main assumptions considered during the case study



                                                   energize | August 2021 | 53
   50   51   52   53   54   55   56   57   58   59   60