Page 72 - Energize October 2022
P. 72

TECHNICAL



           The frequency of oil sampling was increased as the
        transformer was under warranty and the manufacturer
        ultimately had the decision on whether to remove a transformer
        from service for inspection. It is interesting to note the gas
        production after July 1997 showed only a slight rate of rise.
           However, after the oil de-gassing in July 2001, the same
        phenomenon of exponential gas production followed by a
        levelling off was seen (See Figure 3). This can be explained in
        part by the IEC 60599 code that reports that there can be gas
        diffusion losses for in service equipment. However, there is no
        agreement concerning the magnitude.
           There are also reports of gas adsorption by the solid (paper)
        insulation.                                            Figure 8: Damage to the HV winding
           This transformer was ranked as having the highest risk of
        failure, based on the DGA-Total Combustible Gas Profile (See
        Figure 6). The condition was monitored by regular oil samples.   to be at reverse current relays at T23 and T27, which had
        On-line DGA was considered.                               been supplied with metal screws instead of insulated screws
                                                                  originally.
                                                               •  Effectively, as a result of the flash-over, potline voltage (1000
                                                                  V higher) was “connected” to low voltage circuits at the
                                                                  rectifiers. This caused various low voltage equipment failures
                                                                  at the rectifiers and the loss of Potline 1 as well. (The 125 V
                                                                  DC supply is common between Potlines 1 and 2.
                                                               •  The elevated voltage on the potline DC bus resulted in the
                                                                  insulation level of the pot micros being exceeded, damaging
                                                                  a number.

                                                               Fault type. Red phase, HV-LV-core-tank-earth fault
        Figure 6: Total combustible gas profile at July2001
                                                               Consequence of the Failure
        Failure event                                          •  900 MW wiped off the National Grid
        At 16:32, on the 18 November 2005, Transformer T22 failed   •  Potline 1 offline for 75 min
        catastrophically. An urgent DGA sample confirmed that a   •  Potline 2 offline for 145 min
        discharge of high energy (arcing) had occurred (See Figure 7).  •  Major impact to production (output and process stability)
                                                               •  Damage to critical control circuits
                                                               •  Loss of N-1 redundancy in transformer supply


                                                               Disaster averted
                                                               An outage of more than 180 min often leads to a prolonged
                                                               shutdown of an aluminium plant – up to a year.
                                                                  Zero injuries sustained.

                                                               Failure investigation

                                                               On the 21-12-05 the transformer HV and LV winding on the ‘A’
                                                               phase were removed and the core exposed.
                                                                  ‘A’ phase high voltage winding open circuit and flashed to
        Figure 7: DGA trend
                                                               core (See Figure 7).
        When T22 transformer failure developed, the entire sequence of   The flash mark on the A-phase LV winding was on the outer
        events, equipment failures and trips were over in approximately   surface of the disc at the bottom of the winding. The blocks
        one second.                                            underneath the winding showed movement as a result of the
        •  T22 faulted internally caused upstream circuit breaker to trip   flash over between the A-phase HV winding and core.
           and simultaneously induced a high voltage in the rectifier and   Burning in the vicinity of the top core earth strap between
           Potline 2 DC busbar system.                         A and B phases as a result of the fault currents during the HV
        •  The DC busbar system, now at elevated voltage, flashed   flash over.
           over at the point of lowest insulation level. This happened   Overheating of the core. See Figure 9.



                                                   energize | October 2022 | 72
   67   68   69   70   71   72   73   74   75   76   77