          n March this year, Energize reported that the Central Energy Fund (CEF) will
          be investing R1-billion in Renergen’s Virginia Gas Project. This follows an initial
       Iinvestment from the Canadian-based Ivanhoe Mines mining group (see “Funding for
        Phase 2 helium/LNG development and strategic partnership”). Energize spoke recently
        to Renergen’s CEO, Stefano Marani, regarding some interesting technical aspects of
        the project.

        Energize: How did a massive asteroid impact ca 2 billion years ago (the asteroid impact
        that caused the Vredefort Dome) make this deposit a far richer source of helium than
        other deposits in the USA and Qatar?

        Stefano Marani (SM): The Great Bombardment event ca 3,8 billion years ago
        brought all the elements higher than iron in the periodic table (originating from the
        supermassive explosion of a supernova), to earth in massive asteroid showers. The
        Free State received huge amounts of very high concentrations of radioactive uraninite
        (mostly uranium -238) in a layer called the Dominion Group. The massive Vredefort   Renergen CEO, Stefano Marani
        impact 2 billion years ago compacted the Dominion Group and created an impermeable
        seal, thus allowing the helium released by radioactive decay to accumulate at the Free   SM: We focus on the 2P numbers, or
        State site after the impact.                                              the quantity of gas that is commercially
           There is just one big problem in producing helium. Like all the best things in life, it   extractable with a probability of greater
        takes time. Helium production is a slow process. The Virginia Gas Project had 2 billion   than 50%, which is what lenders use.
        years alone with the Dominion Group and a good seal to keep the stuff in. No other   This is not a mining P50 number but
        geological site has had nearly as much time to allow for the radioactive decay to occur for   considerably more conservative. Our
        the simple reason that our tectonic plate we float on, lovingly called Southern Africa, is   methane is 407 billion cubic feet, which is
        far older. The others aren’t nearly as old, so neither is their uraninite or their seal.   enough to create 410 MW of electricity for
                                                                                  20 years nonstop. Another way of looking
        Energize: What are the reserves of liquified natural gas (LNG), and of helium in the   at it, is that it is the same amount of
        Virginia Gas Project?                                                     energy as 11,3 billion litres of diesel fuel.


        Aerial view of Renergen’s Virginia Gas Project.





































                                                    energize | June 2022 | 44