Page 46 - Energize February 2022
P. 46

TECHNICAL



        must cater for start-up kVA which can be four to seven times the   connection of transformer-based loads but this may disturb the
        normal loaded motor current, with current peaks approaching 10   other sensitive loads. The alternative is to use a UPS designed
        times normal current.                                  to limit inrush current but this can only be applied where
           The battery will also be required to deliver current at start-up   the transformer-based load is the only load on the UPS. The
        that could be four to seven times the normal full load current.   general solution would be to size for the inrush current of the
        Increased battery current results in a drop in battery voltage   transformer.
        which could affect the performance of the inverter, so the battery
        characteristics need to be taken into account when sizing for   Condenser input converters
        start-up current. Battery voltage must not drop below inverter   Converters, including variable frequency drives (VFDs), which
        input limits, and this may require a larger battery size than what   incorporate condensers, can exhibit inrush current on start up. In
        would normally be the case.                            some VFD designs current is limited on the application of input
                                                               power by the design of the drive’s pre-charge circuit. The DC bus
        Motor and drive types                                  capacitors are soft charged based on an RC time constant such
        There are three classes of motor which will be encountered in an   that the current at power up will be well below the motor’s full
        industrial network;                                    load current. For other converters, the actual inrush current
        •  Direct online start: The motor is started by connecting directly   of the load needs to be determined. The inrush current of a
          to the full voltage. Start-up current can be four to seven times   converter will generally be of shorter duration than that of a
          the full load current with current peaks of ten times the full   motor application. Many converter circuits incorporate inrush
          load current.                                        current limiting stages.
        •  Soft start: The motor is connected via a soft start controller
          which limits the start-up current and the start–up torque and   Non-linear loads
          speed, or rate of acceleration. The system does not use variable   Although most equipment using electronic converters has
          speed control. The start-up current can be varied to suit the   circuitry that limits the crest factor, there may still be some that
          start-up torque required and generally does not exceed 500%   produces high current peaks. Figure 4 shows a typical non-linear
          of the full load current (Figure 3). When sizing for soft start   load input current waveform. The high current peaks in this
          motors, the actual start current setting needs to be taken into   device can cause overloading of UPS circuitry and need to be
          account, or where this varies with application, the maximum   taken into account when sizing the UPS.
          start current available with the soft start should be assumed.
        •  Variable frequency drives: The motor is connected via a speed   Load calculation
          control device which generally incorporates soft start as a   UPS ratings are normally quoted as kVA and not current so the
          function.                                            start-up current needs to be converted to a kVA figure when
                                                               sizing. In general the maximum current resulting from switching
        Motor drives and soft starters can also cause harmonics in the   on of motors and other devices needs to be determined.
        input current which can affect the sizing of the UPS. The presence
        of harmonics requires derating of the UPS.             •  Single loads: The single load is the easiest to calculate. Sizing
                                                                 will be based on steady state maximum load and start-up load.
        Transformers                                           •  Multiple similar loads: A more complex case, the maximum
        Switching on of down-stream loads connected via transformers   load will depend on the operating schedule of the loads
        results in inrush currents which can be five times the full load   and must cater for steady state full load as well as start-up
        current. One solution is to use the static bypass switch for   loads. Extremes are loads running, and all loads starting up
                                                                 simultaneously. If the operating schedule is not known, the
                                                                 worst-case scenario should be assumed.
                                                               •  Mixed loads: This is even more complex as the inrush current
                                                                 of each load needs to be determined as well as the operating
                                                                 sequence.















        Figure 3: Soft start up currents (Eaton)               Figure 4: Non-linear load current ( Solid State Controls)



                                                   energize | February 2022 | 44
   41   42   43   44   45   46   47   48   49   50   51