Page 46 - Energize September 2021 HR
P. 46

TECHNICAL



        maximum amount of harmonic current to pass through the winding.
        Therefore, the impedance should be as low as practically possible
        (Z% <= 3,5%).
           There should also be no phase shift over the transformer and
        as such the requirement was for a star-star step up 5000 kVAR
        400 V/33 kV transformer. The transformer should also be capable
        of operating at high loading continuously. Another aspect in
        transformer dimensioning is the harmonic voltage distortion at the
        400 V bus. When the active harmonic filter modules inject harmonic
        current through a transformer, there is a voltage drop over the   Figure 5: Active harmonic filter and step-up transformer installation
        transformer at that frequency. Hence, the proper design must ensure
        that the total harmonic distortion at the 400 V bus is kept to a level   Filter configuration
        which does not disturb the operation of any electronics connected   For this specific project, a relatively high level of harmonic current
        to that bus.                                           mitigation was required, making this one of the largest installations
           Finally, the short circuit current at 400 V level needs to be   for this application in the world. Sizing requirements were
        considered. Splitting the 400 V side to two separate busbars   determined to be at 2700 A at 400 V. This required the use of 17 x
        limits the short circuit currents on those busses, which makes the   160 A Merus A2 active harmonic filter modules. All the filter modules
        protection design easier.                              and control hardware were installed into a dedicated modified
                                                               container, properly air conditioned and located in the existing HV
        Protection design parameters                           switchyard. Real-time communication was installed to enable
        The protection system implemented should follow the client’s   monitoring and remote adjustments of the control parameters as
        existing bay control and protection scheme. This includes the   required. The control parameters and tuning of the filter modules
        integration into an existing differential protection envelope and the   can be made in real time from any operator who has access to the
        implementation of main and backup protection. SCADA elements   secure communication network. It is not required to switch off and
        should also follow the existing client system configuration. In this   isolate the system for any control changes to be made and any
        case, the client has a Schweitzer Engineering Laboratories (SEL) bay   changes will take effect immediately.
        control, differential and protection scheme. Therefore, a SEL-787   The system is scalable and can react in real time to any RPP
        protection relay was used as the main protection with a second   or network changes that occur. This is a great benefit over passive
        SEL-751 used as backup protection. A new outdoor 40,5 kV circuit   harmonic filters which are fixed in their tuning point and require
        breaker was installed to switch and protect the transformer and the   large infrastructure changes, which have a long lead time for any
        Merus A2 active harmonic filters.                      modifications to the filtering parameters.




















        Figure 3: New client SCADA screens implemented




















        Figure 4: AHF SCADA screens implemented                Figure 6: Merus A2 active harmonic filter modules



                                                  energize | September 2021 | 44
   41   42   43   44   45   46   47   48   49   50   51