Page 57 - Energize March 2022
P. 57

TECHNICAL



        of usable energy capacity. If a 30-minute   Strategies to future-proof ESS  the capability of a PC-based architecture
        duration is required, then the system’s   Strategy 1: Employ a flexible   is shown below. Many of these
        power capacity must be limited to 5 MW   architecture                     deployments are technically feasible
        so it can continue to yield the same 2,5   There are two primary controls   on a PLC, but would have been much
        MWh of energy capacity. Most PJM battery   architectures for an ESS Energy   more complex and costly, negating the
        system operators responded to the Reg   Management System (EMS): PLC-based   commercial case for deployment.
        D signal changes by simply cutting power   and PC-based.
        in half and reducing system availability.   A programmable logic controller   Strategy 2: Design for flexibility
        However, since revenue is based on   (PLC) is a hardened industrial computer,   One solution for dealing with technology
        capacity and availability, these operational   designed originally for assembly lines.   and market uncertainty is to design for
        changes reduced investor revenue by   PLCs are “hard” systems in that they   ESS flexibility with an augmentation
        greater than 50%.                    are programmed for a specific task,   plan over the ESS project lifetime. In an
           Wärtsilä ES&O, by contrast, made   and they accept limited inputs and   augmentation plan, additional battery
        software and physical site changes to   outputs to accomplish the task. In the   capacity is added to the project site. The
        maintain a high system availability and   context of an energy storage EMS,   augmented battery capacity can be used
        keep the rated capacity of our systems   PLCs are typically designed by inverter   to supplement planned battery capacity
        greater than 50%. We did this by re-  manufacturers and coded for a specific   losses due to battery degradation, or to
        evaluating all the trade-off decisions   inverter and battery technology.   provide incremental capacity if future
        that go into ESS operation. For example,   Modifications are possible, but they   market conditions support a larger
        because the Reg D signal change increased   take significant time and effort and   system.
        energy throughput, we reduced ESS    typically require an engineer onsite for   While augmentation plans make
        temperature, which decreased degradation   months at a time. This makes the cost   sense in concept, few installed energy
        but also decreased round-trip efficiency.   of PLC modification relatively high.  storage systems today have been
        Because the signal change modified     A personal computer (PC)-based     planned for augmentation. As such,
        the energy neutrality condition, we   controller is built on multi-purpose   there is no long-term track record of
        modified our state-of-charge management   industrial servers and is controlled by   augmented battery storage systems.
        algorithm, which impacted energy     software. The PC-based architecture   In addition, there are different schools
        throughput and system performance.   facilitates complex operation and    of thought about how to safely and
           These changes were enabled by     optimization and allows for updates to   effective augment ESS projects. Wärtsilä
        future-proofing with an architecture of   be delivered faster and at lower cost.   is one of the few market participants
        flexible controls, which we will discuss   Wärtsilä’s GEMS controls platform is   to have installed an ESS that has been
        next. While future-proofing saved Wärtsilä   designed with a technology-neutral   planned for augmentation, and Wärtsilä’s
        customers millions of dollars in PJM, other   architecture, meaning that the same   position is that there is a right way and
        PJM systems faced tremendous losses.   controls platform can be used with any   a wrong way to design for flexibility with
        Investors looking at the experience of   battery and inverter technology with   an augmentation plan.
        the PJM merchant market for Reg D will   minimal configuration.             The right way to design for flexibility
        use caution when entering into future   The company tests all software    is to plan the ESS layout for inverter-
        merchant markets for ESS.            modifications on a virtual machine that   based augmentation. This design
           Faced with a limited track record of   replicates the technology characteristics   requires leaving sufficient space for
        the ESS installation base as well as market   of each piece of hardware. Updates   additional battery racks and designing
        uncertainty, how can an ESS investor   are performed only after the software   wiring and cable trays for the future state
        mitigate risk? The only option is to future-  has been fully debugged in a lab   of the system, where some racks have
        proof current ESS investments to plan for   environment and are then installed   moved and additional racks are added.
        changes in the future.               remotely via a secure VPN and require   With an inverter-based augmentation,
                                             only five minutes of downtime.       batteries will be wired in parallel only
        Energy storage projects can be future-  The PC-based flexible architecture   with other batteries of the same vintage.
        proofed by:                          enables various degrees of flexibility that   The older batteries will have a similar
        •  Installing a flexible controls architecture  each contribute to ESS future-proofing.   state of health and therefore they will
        •  Planning the right way for battery   In PJM, the flexible architecture allowed   have similar resistance and current
          capacity augmentation              the company to react quickly to adverse   output profiles.
        •  Tracking ongoing operation with a   changes in the market. In other cases,   The new batteries may have different
          flexible warranty                  the flexible architecture has enabled it to   characteristics, benefitting from higher
                                             easily repurpose ESS assets when market   performance, lower cost and a smaller
        We see flexibility as the number one   changes allowed for incremental value.   footprint, thus requiring a smaller initial
        factor.                              A table of case studies demonstrating   capacity than batteries from the original



                                                    energize | March 2022 | 55
   52   53   54   55   56   57   58   59   60   61   62